Here we come to the stage of Building roof.. Yes, So
far we have completed the following stages:
1.Basement,
2.Building walls Up to Linden,
3. Linden Concrete
4. then walls again
5. Roof Concrete
So we posted the pic related to basement ground in the last Post.
Let me explain in Detail; How we build Up to this stage
Constructed Beams to strength the Building & walls constructed
up to 10 feet, Used 15mm Steels with the Trusted brand to make our pillars so
strong
Building Walls is the next stage as we all Know; Used the Bricks
to build walls.
He we goes Our plan ;
Kitchen measures : 10*10
Dining Hall Measures:10*10
Master Bedroom Measures:16*10
Attached Toilet& bathroom Measures:8*5
Pooja Provision Done
Bedroom#2 Measures:10*11
Portiko Measures: 10*16
Outer Bathroom Near by Staircase Measures:5*4
Linden Concrete: It is done using the correct ratio of cement
& M-Sand, jalli
Again walls Upto 2.5 feet is constructed, then Roof Concrete is
done.
Meanwhile we have got PoweSupply, Borewell is fixed aound 450 feet
with generous amount of water and PowerTech Pump submersimble one is fixed to
get the water.
We have constructed Sewage Tank and Water Tank as well; Yes.. why
so wait? Visit our Construction Building and Book Ur Dream House
with us!!!